PROGRESS UPDATE ON 21/10/2022

CONSTRUCTION PROGRESS UPDATE ON 21/10/2022

Zone 1:

  • B2: 100% done Completed 100% of B2 concrete pouring on 29/01/2022
  • B1: 100% done Completed B1 floor concrete pouring for the indoor area. Cumulative 2456/2456m³ ~ 8857/8857m² – 100%
  • T1: 72% done T1 floor concrete pouring: Cumulative 1470/2042m³ ~ 6370/8857m² – 72%

Zone 2:

  • B2: 54% completed Completed B2 concrete pouring 3870m²/7151m² reaching 54%
  • B1: 15% done Completed B1 floor concrete pouring for the indoor area 215m³ ~ 900m². Currently performing formwork and steel reinforcement for B1 floor: 1600m²