CONSTRUCTION PROGRESS UPDATE ON 21/10/2022
Zone 1:
- B2: 100% done Completed 100% of B2 concrete pouring on 29/01/2022
- B1: 100% done Completed B1 floor concrete pouring for the indoor area. Cumulative 2456/2456m³ ~ 8857/8857m² – 100%
- T1: 72% done T1 floor concrete pouring: Cumulative 1470/2042m³ ~ 6370/8857m² – 72%
Zone 2:
- B2: 54% completed Completed B2 concrete pouring 3870m²/7151m² reaching 54%
- B1: 15% done Completed B1 floor concrete pouring for the indoor area 215m³ ~ 900m². Currently performing formwork and steel reinforcement for B1 floor: 1600m²